The Madison Strong Field complex includes a synthetic surfaced multi-purpose field, playing field lighting and a 2,000-person capacity grandstand seating structure.
Problem
The Challenges
1
Munger was contracted to build two identical 1,380 SF wood and steel framed structures, which act as field houses, restrooms, storage areas and a concession stand.
Solution
The Resolutions
1
The team began the project by pouring the slab onto the already existing foundation for the field houses.
2
The wood and steel framing were then erected and cupolas were installed on the roofing for venting purposes.
Outcome
the final product
All interior work was then performed including interior wall framing, siding, door/window installation, trimming and painting. Munger’s subcontractors performed all of the plumbing work for the restrooms, as well as fixture and bathroom partition installation. Electrical work for the two buildings was also completed by Munger subs, and lastly, epoxy coating was applied to all the interior flooring.
Munger Construction greatly appreciates the Town of Madison for the opportunity to contribute to such an impressive public sporting campus!