Portfolio

North Haven DPW

Elm Street, North Haven, CT 06473
Printable Version

What We Did

Project Overview

Design-Build Municipal

Renovation

Gallery

See Our Work

    Testimonial

    What the client had to say about us

    Testimonial
    "Munger built our new Sanitation Equipment Storage Building along with various site improvements. This helped us to consolidate operations personnel and sanitation equipment at a single location, which will enhance cohesiveness of the Field Operations Division and will better support our town’s infrastructure needs. This is the third time during the past two years that Munger has done work for the town under the state’s ezIQC program."

    Lynn Sadosky

    Director, North Haven DPW

    Case Study

    The Situation

    Pat Munger Construction Company, Inc. completed each project within budget and on or ahead of schedule. According to Public Works Director, Lynn Sadosky, “This will better support our town’s infrastructure needs.”

    Problem

    The Challenges

    1

    North Haven Public Works facilities required updates and repairs following hurricane damage.

    2

    Lost lease for the sanitation facility.

    3

    Need to bring a maintenance facility into compliance with OSHA regulations.

    Solution

    The Resolutions

    1

    Roof repairs were made.

    2

    Design and construction of a storage barn for road de-icing salt.

    3

    Design and construction of a 5,000 SF Varco Pruden pre-engineered steel building for sanitation crews and equipment.

    4

    Installation of a maintenance shop ventilation system to remove engine exhaust and other harmful vapors.

    Outcome

    the final product

    The North Haven Department of Public Works Campus Improvements project was selected for the 2012 Harry H. Mellon, Award of Excellence in Job Order Contracting for the Northeast Region. The Munger team is proud to have been selected as the 2012 Northeast Region award winner.