What We Did

Project Overview

Founded in 1954, the Guilford Veterinary Hospital has been recognized by the American Animal Hospital Association (AAHA) for quality of care provided by veterinarians who diagnose and treat animals using the most up to date methods so that pets may lead the healthiest and happiest lives possible.

Veterinary

New Construction

Gallery

See Our Work

    Testimonial

    What the client had to say about us

    Testimonial
    "Munger installed a new roof atop the old one prior to beginning the renovation. They worked around our need for space and we appreciated that the same foreman was on the job for the entire project. He continuously made helpful suggestions during the six month project. Unlike experiences I’ve had with other builders, Munger’s subcontractors arrived on time 95% of the time and Munger showed a consistent knack for bringing in their subcontractors for quick needs that weren’t included in the project plan."

    Dr. Ralph Schoemann

    Owner, Guilford Veterinary Hospital

    Case Study

    The Situation

    A former residence, built in the days before zoning regulations, served as the home of the Guilford Veterinary Hospital for 19 years until 1973 when it was renovated to support 3 veterinarians. Since then it became an undersized and outdated medical facility with interior electrical hazards and expansion limited by exterior ledge that was higher than the finished floor level. By 2005, with 6 vets and a full staff, they needed to benefit from new technology in a larger, brighter and more open environment that is convenient for staff and customers. The owners were referred to a Louisiana architectural firm that specializes in designing veterinary facilities and who developed the winning plans in the Veterinary Economics hospital of the year issue. They were ready to customize this template to fit their needs. Munger Construction completed extensive expansion, renovation, repair and upgrades to create a larger, brighter and more open environment that is convenient for staff and customers and includes all the latest in new technology.

    Problem

    The Challenges

    1

    This wintertime renovation had to be completed without any interruption in day to-day business activities with particular attention to staff and client safety and full time availability of surgery and emergency areas.

    Solution

    The Resolutions

    1

    A dual-purpose roofing system provided a canopy under which the old roof was removed while staff and customers were protected from adverse winter weather conditions.

    2

    The new roof that covers the renovated and enlarged 7,000 sq-ft facility looks as if it were framed as one.

    Outcome

    the final product

    According to Raccio, “It was a challenging job. They had to remain in business while we were redoing the entire facility. They didn’t shut down for a minute.” A renovated and expanded facility with attractive cabinetry, windows and siding looks like one building under one uniform roof with appropriate egress and handicap accessibility. A standout entrance, expanded front desk, lobby and reception area, and 3 additional examining rooms are major improvements from the original building. The 5-zone HVAC provides a consistently comfortable environment compared to the original 2-zone system. People are more productive and the facility is easier to keep clean. Customers and staff have favorably commented about its brightness, cleanliness, comfort, spaciousness, and optimized traffic flows.